Steam and Condensate
The above video is also steam and condensate, with 2 high pressure lines and 2 low pressure lines.


This installation was Barkers Laundry, Bournemouth in which they wanted a full upscale of steam supply to allow for higher wash and dry capacity. The works took us 8 weeks to complete and included a new boiler, water tank, condensate tank, blow down vessel, 4 x dryers, 5 x washers and 6 x presses. Including all the steam and condensate we also installed a brand new BCW line, air line and drainage from the washers.
Contract Value - £76,752.39


This Installation was at DS Smith, Devizes in which they wanted a complete replacement of their current main steam and condensate lines (high pressure) and also a brand new low pressure steam and condensate line to allow for new technology provided by Baveira Ltd. The pre-fabrication of these works started in January 2023 and the installation was finished by the middle of April 2023.
All works were signed off by an expansion specialist; Minikin and Sons Ltd in which they quoted 'The entire installation, which was inspected by Minikins, was up to standard and of high quality'.
10% of welds were subject to ultrasonic inspection by Capital NDT in which they all passed.
Contract Value - £269,081.48
This installation was at NWSSP's central laundry, Llansamlet. Their old steam and condensate pipework had become unsafe due to its condition. Therefore we installed a brand new steam and condensate system in stainless steel. This was a 6" steam and a 3" condensate main with smaller submains to supply the ironers and stand alone dryers. We also did the full rip out of the old system.
Project Programme - 4 Months
Contract Value - £175,307.29
LTHW/CHW/Gas
This was the first floor gantry in which 5 x AHUs were positioned on. All of them have HTG and CHW supplied to and our work extended to the plantroom and distribution all over the internal of the building. This included the HTG and CHW supply to 57 FCUs.
Project programme -11 Months
Contract value - £675,059.37
This is the plantroom for the HTG supply for 4 x block of flats in Acton, London. We completed this, the BCW plantroom, and all riser and distribution pipework for both High pressure and Low pressure HTG and BCWS.
Project programme -25 months
Contract value - £908,107.14
This installation was at Bromley Moore Dock, Everton FC's new stadium. There we installed part of the new HTG system. It was from the plantroom to MDPE connections left just by the pitch. These works were done in ISO stainless steel which means they have the same OD as steel pipes. The primary pipework was 6" and the secondary pipework was 4".
Project programme - 4 weeks
Contract Value - £55,465.23
We have also installed the whole plantroom and distribution pipework to 5 x AHUs in the roof at HMP Rye Hill. This also included a large 10" gas run to feed the 6 x boilers and 1 x CHP in the roof. We do not have any pictures of the work as you are not allowed your phones on site.
Project programme - 4 months
Contract Value - £72,657.08
Gas
These works were at HBPO, Banbury and were a Gas main replacement as their old pipework was leaking and actually flaking off due to the rust. These works took 8 days to complete, the first weekend was to remove the pipework and measure up for pre-fabrication and the next weekend to fit.
Contract Value - £11,517
Welds
All of our welding is certified to ISO 9606-1. Certificates can be issued before work commences if required.

